10th Avenue SE Bridge Replacement
Summary
The new bridge is asphalted on both ends and nearly paid off — this final big payment includes $87,000 in penalties the contractor absorbed for delays. Only retainage remains.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Jun 1, 2026.
Impact analysis
$508,318.06 paid, including an $87,000 penalty deducted from the contractor for schedule delays.
Drivers crossing 10th Avenue SE get a new bridge with railings, sidewalks, and fresh asphalt.