Proposed BMU rate increases
BMU is proposing a 3.5% residential electric increase (about $92 to $95.20 on a typical 800 kWh bill) and a 4% water increase, with wastewater unchanged.
MRES wholesale power agreement extension
BMU's utility board voted to extend its supplemental power contract with Missouri River Energy Services from 2054 to 2064. The deal guarantees power supply as Brookings grows, though MRES power costs about twice as much as the city's cheaper WAPA allocation.
Missouri River Energy Services Agreement
BMU's utility board voted to extend its supplemental power contract with Missouri River Energy Services from 2054 to 2064. The deal guarantees power supply as Brookings grows, though MRES power costs about twice as much as the city's cheaper WAPA allocation.
2026 Drainage Improvements Project
A $324,872 contract with BX Civil and Construction will replace the Village Square drainage channel and the detention basin inlet at 15th Street South and Seventh Avenue, with work starting this fall.
BMU solar array and future power needs
The 5-megawatt solar array northeast of Brookings finished pilot testing and should be online within a couple of months. BMU expects a big jump in power demand over the next decade from expanding industries and new housing.
New Brookings water treatment plant
Council Member Avery toured the new $115 million water treatment plant at its public open house. The facility can produce about 6 million gallons a day with 2 million gallons of underground storage and on-site daily water-quality testing — securing Brookings' drinking water supply for years to come.
Arbor Hills detention basin ownership
The city was considering accepting ownership of detention basins in the Arbor Hills Subdivision, which manage stormwater drainage and require ongoing maintenance.
BMU Transmission Line and Watering Rules
BMU is planning a new transmission line through Aurora plus two substations to add power redundancy after the derecho. Summer yard watering is back to a four-day-per-week schedule.